Works to be carried out  THE INVESTOR  LONG JIANG IPD  GOVERNMENTAL ORGANIZATIONS 
Reservation of land Investor signing land lease agreement with Long Jiang IPD
Paying deposit of 10% of total land rental to Long Jiang IPD
Applying for
investment certificate
Preparing necessary documents
(download files)
Submitting to Tiza for
evaluation and approval
Supporting the investor, when
required
1/. For the project with investment capital under 100 billion VND:
Evaluated by: Tiza; Time: 1 week
2/.For the project with investment capital above 100 billion VND:
Evaluated by: Provincial People’s Committee, Time: approximately 1->3
months depending on technology complication of each project
After investment certificate is issued Investor paying to Long Jiang IPD the 1st payment of rental  Click here to view a sample of certificate
Registering for stamp
and tax code
Filling forms with signatures of
the investors
Supporting the investor, when
required
Place: at Tiza office
Time: 1 week
Signing official lease contract and land delivery Signing the official land lease contract with Long Jiang IPD The land lease contract is public notarized by Tiza, Time: 1 or 2 days
Investor receiving land delivery from Long Jiang IPD
Investor paying to Long Jiang IPD the 2nd payment of rental
Applying for
construction permit
with 3 documents:
1/Environment impact
evaluation & solution for approval
Supporting the investor, when
required
Place: Department of Natural Resources & Environment
Time: 45 days
2/ Fire prevention solution for approval Supporting the investor, when
required
Place: Police of Fire Prevention & Fight
Time: 1 week
3/ Factory Plan & Construction design for approval Place: at Tiza office
Time: 1 week
Construction Investor’s constructor signs service contracts with Long Jiang IPD for temporary supply of electrictity and water during construction Click here to view General Regulation on factory construction in Long Jiang Industrial Park
Starting construction Supporting the investor, when required. After investor determines contractor and construction cost, may entrust LJ to construct (free entrust fee of construction management)
Investor coordinating with Long Jiang IPD for connection points
of power & water supply, waste water discharge
Transfer of land use
right certificate
After the investor having paid
90% of total land rental
Applying for transferring land
use right certificate to the
investors
Handled by: Province’s Department of Natural Resources
Time: about 1 month
Investor paying to Long Jiang IPD the 3rd payment of rental
Investor receiving the Land Use Right Certificate from Long Jiang IPD   Click here to view a sample of certificate
Operation Investor signing with Long Jiang IPD for service contracts of power & water supply, treatment of wastes, etc.
 Starting operation Supporting the investor, when
required
Under governmental management by Tiza
thiết kế thi công gian hàng hội chợ triển lãm
thiet ke thi cong gian hang hoi cho trien lam
exhibition booth contractor in vietnam
phan mem quan ly khu cong nghiep
phần mềm quản lý khu công nghiệp
phan mem quan ly tinh dien nuoc
phần mềm quản lý tính điện nước
giai phap bigdata
giải pháp bigdata