Works to be carried out  THE INVESTOR  LONG JIANG IPD  GOVERNMENTAL ORGANIZATIONS 
Reservation of land Investor signing land lease agreement with Long Jiang IPD  
Paying deposit of 10% of total land rental to Long Jiang IPD  
Applying for
investment certificate
Preparing necessary documents
(download files)
Submitting to Tiza for
evaluation and approval
Supporting the investor, when
required

Evaluated by: Provincial People’s Committee, Time: approximately 1->3
months depending on technology complication of each project
After investment certificate is issued Investor paying to Long Jiang IPD the 1st payment of rental  Click here to view a sample of certificate
Business license registration, engraving the seal Fill in the form with the signature of investor according to Enterprise Law 2020 Supporting the investor, when
required
Place: Public Administration Center
Time: 1 Week.
Signing official lease contract and land delivery Signing the official land lease contract with Long Jiang IPD

Land Lease Contract is notarized at authorized notary public according to regulations

Time: 1 or 2 days

Investor receiving land delivery from Long Jiang IPD  
Investor paying to Long Jiang IPD the 2nd payment of rental  
Applying for
construction permit
with 3 documents:
1/Environment impact
evaluation & solution for approval
Supporting the investor to find a consulting unit when required Place: Department of Natural Resources & Environment
Time: 45 days
2/ Document for firefighting approval Supporting the investor to find a consulting unit when required Place: Police of Fire Prevention & Fight, One – door department
Time: 1 week
3/Construction license according to regulation Public Administration Center   Place: at Tiza office,Public Administration Center
Time: 1 week
Construction Investor’s constructor signs service contracts with Long Jiang IPD for temporary supply of electrictity and water during construction Click here to view General Regulation on factory construction in Long Jiang Industrial Park
Starting construction Supporting the investor, when required. After investor determines contractor and construction cost, may entrust LJ to construct (free entrust fee of construction management)
Investor coordinating with Long Jiang IPD for connection points
of power & water supply, waste water discharge
Transfer of land use
right certificate
After the investor having paid
90% of total land rental
Applying for transferring land
use right certificate to the
investors
Handled by: Province’s Department of Natural Resources
Time: about 1 month
Investor paying to Long Jiang IPD the 3rd payment of rental  
Investor receiving the Land Use Right Certificate from Long Jiang IPD   Click here to view a sample of certificate
Operation Investor signing with Long Jiang IPD for service contracts of power & water supply, treatment of wastes, etc.  
 Starting operation Supporting the investor, when
required
Under governmental management by Tiza
thiết kế thi công gian hàng hội chợ triển lãm
thiet ke thi cong gian hang hoi cho trien lam
exhibition booth contractor in vietnam
phan mem quan ly khu cong nghiep
phần mềm quản lý khu công nghiệp
phan mem quan ly tinh dien nuoc
phần mềm quản lý tính điện nước
giai phap bigdata
giải pháp bigdata